Minutes of the Orion Technical Meeting: Sept.
27, 2000
===============================================================
Location: Room 144D (Beige Room),
Admin. and Engin. Bldg., SLAC
Present:
Robert Noble, Dennis Palmer, Robert Siemann, Dieter Walz
Minutes recorded by: Robert Noble
1. Meeting time:
Future meetings will be on Mondays, 10
AM in the Beige Room
(Room 144D) in the A&E Building
(Bldg. 41) at SLAC.
2. Discussion of the next steps in the Orion
project:
- The assumption is that we will receive
by October 30 an NSF
invitation to submit a full proposal due
January 26, 2001.
Award announcement will occur by August
1, 2001 (10 months
from now) at which time we start construction
of Orion at
the NLCTA.
- Before construction start, the Orion
project will require
a baseline design, a final Work
Breakdown Structure, Schedule
and Cost Estimate. This enables all
participants to understand
their tasks and resource needs.
- A short Technical Design Study (TDS)
with contributions from
the various participants in the
collaboration is a proper
vehicle to address the above issues. R.
Noble will act as
editor and begin contacting
collaboration members to act as
writers. A draft "Table of
Contents" has been placed on the
Orion website
(http://www-project.slac.stanford.edu/orion)
within the Collaboration's special page
(access by Collaboration
members only via password available from R. Siemann,
siemann@slac.stanford.edu). There may be
more subsections at
Level 3 than this draft table shows
depending on text supplied
by the writers. A TDS document of about
50-75 pages is thought
to be adequate, so contributions from
individual writers should
be brief and to the point. The target
date for the first TDS
draft is November 17, 2000. Much of the
material generated for
the TDS can be used in the NSF proposal.
3. Roundtable discussion of Orion design
assumptions for the TDS:
- The Orion RF Gun is assumed to be a 1.6
cell, S-band (2.856
GHz), emittance compensated
photoinjector, based on the well
known BNL/SLAC/UCLA design, and driven
by a frequency-tripled
Ti:Sapphire laser in a Class 10K clean
room. Whether the new
injector is physically interchangeable
with the present X-band
NLCTA gun or intalled as one leg of a Y
magnetic switch
(dipole) depends on a beam dynamics study as well as reaching
agreement with the NLCTA management.
- The Low Energy Extraction Line at 50 MeV
will leave the NLCTA
enclosure at a 20 degree angle,
necessitating the boring of a
beampipe hole through four of the interlocking shield blocks.
A beam physics design will be performed
to confirm that a
beamline with quadrupoles on either side
of the wall can
transport the beam properly.
- The Laser Room 1 layout shows it to be
20 feet by 40 feet,
which is large for the compact,
commercial laser. It was
suggested that we keep the room
oversized to provide added
lab space for other Orion work and
upgrades. Laser Room 2 for
experimenters will be expanded in the
design to allow for up
to two laser systems with separate
enclosures. The interlock
system will be designed with sufficient
flexibility to allow
personnel access to lasers not in use
for beam-on experiments.
The laser room at Bldg. 407 was cited as
an example to use
for estimating floor space and
utilities.
- An Experimental Staging Area for users
will be needed in the
vicinity of the experimental halls.
Experimental equipment
can be mounted to support girders and
tested prior to
installation in the halls. A new SLAC
lab building is being
planned for the area immediately
northeast of End Station B,
and R. Siemann has requested Orion space
there from
S. Williams, SLAC Experimental
Facilities Dept.
- The present concept for experimental
operations in the Low-
Energy Hall envisions space for three
installed experiments
on the floor, but only one taking beam
during a run period
lasting a few days. Beam would thus be
time-shared between
the experiments with one taking data and
the other two
analyzing data and preparing for their
next run. This
arrangement simplifies the Control
System to one appropriate
for single-mode operation and no fast
beam sharing.
- In order to insure that there is no
interference with the
Laser Room 1 or the 20 degree Transfer
Line to the Low Energy
Hall, NLC management will be consulted
on their need for
floor space inside End Station B for the
so-called "8-pack"
RF System Test.
- A critical part of the Orion TDS will be
an estimate for
water and power utilities. As the Laser
Systems, RF System,
Transfer Lines and Experimental Halls
are defined, a power
and water supply budget will be
tabulated with the aid of
the SLAC engineering staff.
- D. Palmer, D. Walz and R. Noble will
make a fact-finding
trip to the Accelerator Test Facility at
Brookhaven National
Laboratory on October 26 - 27, 2000 in
order to learn about
that facility's design, utility and
space requirements,
operational procedures, and construction
and operational
costs.
==================================================================