E163 civil
constr. meeting 7/28/04.
Attendees:
R. Siemann,
E. Colby, D. Palmer, S. Zalog, D. Amador, H. Shin, D.
Walz, R. Noble.
Dino Amador brought final
version of electrical/cable tray layout and panel schedules for B225 connection
to ESB.
Sam Zalog
will install the disconnects on B225; work should be
complete by Friday 7/30.
All cable tray
is available, and brackets expected to arrive by Friday or Monday 8/2,
according to Dino. Bayspan electricians are busy with
work associated with shutdown preparations. Dino will contact Leanne Robinson
to determine if additional Bayspan personnel are
available to work on E163 tasks.
Priority will be given to
electrical work needed to provide power connections for the
E163 laser
clean room installation, which is scheduled to occur during August 19 - Sept
14. B225
electrical work will be done as electricians are available.
Harry Shin brought the Flowstar frame drawing. Mike Bennet
of Flowstar will visit the site Thursday 7/29 to
discuss a possible disparity in frame dimensions.
Seismic documents are
scheduled to be submitted Thursday by Flowstar, and
will undergo a SLAC peer review.
Harry sent a sketch of the
B225 fire sprinkler layout to Cal Protection to aid in their hydraulic
calculations for the sprinkler reconnection. Harry will also look into the
requirements for the deck width and ramp pitch outside B225.
Additional information about
the E163 experiment can be found at:
http://www-project.slac.stanford.edu/e163/
Meeting minutes posted at:
http://www-project.slac.stanford.edu/e163/MeetingMinutes/default.htm
*******************************************************