Minutes of the E163 Civil Construction Meeting, 2/26/04.

 

Attendees: E. Colby, J. Sevilla, R. Principe, H. Shin, P. Rodriguez, D. Palmer, R. Noble, D. Amador, C. Corvin

 

1. Laser room electrical requirements were discussed with D. Amador. The

new E163 45 kVA transformer outside ESB is intended as the source of all

clean power for laser room and other needs associated with the experimental

hall. Consequently it was decided not to install an additional clean power

conditioner in the laser room. Lighting and computer power will come from

an existing 110V "dirty power" line. Three clean power pendant outlets above the laser tables are requested. E. Colby will provide D. Amador a revised

sketch of the laser room clean power and dirty power needs. Amador and

R. Principe will modify the electrical spec drawing accordingly for inclusion

in the draft laser room bid package.

 

2. J. Sevilla reported that parts are on order to arrive the week of March 1 for the E163 hall water manifold. Purchase req is in for plumbing contractor and work expected to start by March 3. NLC 8-Pack will be off part of

next week so the fire alarm can be turned off to allow plumbing tie in to the

8-Pack manifold stub out. Sevilla will include supply-return pressure gauges

to the manifold in the hall.

 

3. Sevilla will meet with Mike Racine, EFD, today 2/26 to schedule start of

installation of modulator cooling manifold instrumentation.

 

4. H. Shin has started a draft laser room bid package with the goal of having the pacakge done by March 10. We will review the status at the March 3 civil meeting.

************************************************************