Minutes of
the E163 Civil Construction Meeting,
Attendees: D. Amador, R.
Principe, H. Shin,
D. Palmer, R. Siemann, R. Noble, D. Walz
1. Ricky Principe brought
the existing E163 electrical wiring layout which
has a preliminary sketch by
Mario Machicao for the laser room electrical supply.
Ricky will create a file of just that section, and we will use
it in the bid package. We will
review the sketch at the next Civil meeting
and revise it to agree with our
present specs with Dino Amador's assistance.
2. Dennis Palmer will review
the laser room electrical power requirements both for loads inside and outside
the room, and in terms of the breakdown of clean and dirty power.
3. It was agreed to use the
laser room drawing of Ron Rogers for the bid
package with minimal electrical
detail. It was agreed that a text description of our laser room electrical
needs is adequate for the bid package, other than the sketch to be included
from Item 1 above.
4. Dino Amador will arrange
to have the vertical cable tray extensions installed above the E163 modulator
at ESB.
5. We will invite Rob Reek
to the next Civil meeting to begin a discussion of the fire detection and
suppression for the laser room.
6. Javier Sevilla could not attend but left us drawings of the E163
hall
water manifold for review.