**********************************************************

Minutes of the E163 Civil Construction Meeting, 2/4/04.

 

Attendees: D. Amador, J. Sevilla, K. Jobe, P. Rodriguez,

D. Palmer, R. Siemann, E. Colby, R. Noble

 

1. Dino Amador reported that Francisco Castillo has ordered the correct vertical tray elbows for the east-wall cable tray. Delivery scheduled for Monday 2/9.

 

2. Eric Colby will determine the length of vertical cable trays needed above the

modulator for future installation.

 

3. Javier Sevilla ordered the four Proteus flow switches for the modulator cooling instrumentation. Switch delivery expected Tuesday 2/10. Presssure gauges are to

be ordered also and delivery expected next week. Sketch of flow switch layout was distributed. Installation to be done after Feb. 16.

 

4. Javier Sevilla said drawings for the E163 hall piping will be done probably by Wednesday 2/11. He plans to get the P.O. in next week for start of installation on about Feb. 17.

 

Additional information about the E163 experiment can be found at: http://www-project.slac.stanford.edu/e163/

*******************************************************************