The Research Support Building and Infrastructure Modernization Project
Project Factsheets
Warehouse/User Building (Bldg. 028)

The Warehouse/User Building (Bldg. 028) will undergo a significant renovation between January 2011 and October 2011. This renovation will add a combination of hard-walled offices and cubicle work-stations to the entire 20,000 square-foot building. The construction will also add ADA compliant access, restrooms, break rooms, huddle rooms, and utility rooms (mechanical, electrical, IT, etc.). The salvage yard, located on the North side of the Warehouse/User Building, will be converted to parking. SLAC will seek LEED® Gold Certification for the newly renovated building.

WUB Timeline
June 2010 Design scheduled to be complete
June 2010 Construction documents ready for bid
Jan 2011 Construction Award
Feb 2011 Construction Mobilization
Oct 2011 Construction Complete
Nov 2011 Building Occupancy
Building Floorplans
Building Renderings
Warehouse/User Building, Building 028