The 230kv Circuit Switchers #265 and #275
Replacement Project replaced damaged and aging equipment by
providing new disconnect switches with load interrupters at the
SLAC 230kv tower 1.
The damaged 265 circuit switcher and the 275
circuit switcher were removed and replaced with new
equipment. The final
configuration returned the site reliability back to two
functional switches.
The construction took place within the Scientific Program
shutdown period of August, 2012.
The USA Easement from Bear Gulch Road to the Tower has
been repaired to a usable and maintainable state.
Project Timeline | |
Aug 2012 | Construction start |
Sept 2012 | Construction complete |