NLC ENGINEERING ESTIMATE

PROJECT: NLC Delay Line WC475 W/ Eyelets 500 GeV

DATE: 6/19/98

ENGINEER: J. Weinberg

REVISION:

B&H

ED&I

MATERIAL

LABOR

ITEM

MEAS

# UNITS

UNIT COST

TOTAL

MEAS

# UNITS

UNIT HRS

TOTAL HRS

$/HR

TOTAL

MEAS

# UNITS

UNIT HRS

TOTAL HRS

$/HR

TOTAL

WC475 Delay Line flg.-flg.

WC475 (5 in. Dia) Cu

14m

10,000

723

7,230,000

Cu end collar

ea

20,000

8

160,000

S.St. eyelet

ea

20,000

10

200,000

eyetet adaptors/blanks

ea

5,000

15

75,000

eyelet clamps

ea

2,500

75

187,500

tin seals

ea

25,000

1

25,000

75 l/s ion pumps

ea

3,400

1,000

3,400,000

Braze Furnace

ea

2

100,000

200,000

Glow Discharge Cleaning

GDC Stations

ea

15

100,000

1,500,000

0

0

0

0

Tech labor for GDC

0

4.5 hr/pc

10,000

4.50

45,000

40

1,800,000

0

0

Vac. Engr.

4,000

57

228,000

Designer

2,000

39

78,000

Engineering Design

Mechanical Fab

hr

10,000

0.25

2,500

56

140,000

QC

hr

5,000

0.50

2,500

60

150,000

Precision Assy

hr

20,000

0.25

5,000

56

280,000

Plating and Cleaning WC293

hr

10,000

0.25

2,500

100

250,000

Plating and Cleaning

hr

40,000

0.01

400

100

40,000

Field Welding

hr

20,000

0.25

5,000

56

280,000

Torch Brazing

hr

20,000

0.25

5,000

56

280,000

Mech Techs

hr

10,000

0.25

2,500

40

100,000

SUBTOTAL

12,977,500

3,320,000

306,000

TOTAL B&H

$16,297,500

TOTAL ED&I

$306,000

PROJECT TOTAL

$16,603,500