NLC ENGINEERING ESTIMATE

PROJECT: NLC WC293 W/ Eyelets 500 GeV

DATE: 6/19/98

ENGINEER: J. Weinberg

REVISION:

B&H

 

ED&I

MATERIAL

LABOR

ITEM

MEAS

# UNITS

UNIT COST

TOTAL

MEAS

# UNITS

UNIT HRS

TOTAL HRS

$/HR

TOTAL

MEAS

# UNITS

UNIT HRS

TOTAL HRS

$/HR

TOTAL

Delay Line flg.-flg.

WC293 (3 in. Dia) Cu

10m

1,792

294

526,848

Cu end collar

ea

3,584

6

21,504

S.St. eyelet

ea

3,854

8

30,832

Eyelet adaptors/blanks

ea

896

15

13,440

Eyelet Clamps

ea

896

50

44,800

Tin seals

es

2,000

2

3,000

Glow Discharge Cleaning

GDC Stations

ea

2

100,000

200,000

Tech labor for GDC

0

4.5 hr/pc

1,792

4.50

8,064

40

322,560

Vac.Engr.

250

57

14,250

Designer

200

39

7,800

Engineering Design

Mech Fab

hr

0

0.00

0

0

0

0

0

QC

hr

0

0.00

0

0

0

0

0

Precision Assy

hr

3,858

0.25

965

56

54,012

0

0

Plating and Cleaning WC293

hr

1,792

0.25

448

100

44,800

0

0

Plating and Cleaning

hr

8,960

0.01

90

100

8,960

0

0

Field Welding

hr

3,858

0.25

965

56

54,012

0

0

Torch Brazing

hr

3,858

0.25

965

56

54,012

0

0

Mech Techs

hr

1,792

0.25

448

40

17,920

0

0

SUBTOTAL

840,424

556,276

22,050

TOTAL B&H

$1,396,700

TOTAL ED&I

$22,050

PROJECT TOTAL

$1,418,750