1.3.2

Main Linac Beam Lines

($000)

1.3.2.4

Sustaining Engineering (CD3-CD4)

Labor hrs

Labor $

Material $

totals

Structure

34,503

$ 1,897

$ 780

$ 2,677

Magnet Systems

9,797

$ 875

$ 56

$ 931

Vacuum systems

9,137

$ 505

$ -

$ 505

Diagnostic Regions

2,097

$ 838

$ 4

$ 842

Total

55,533

$ 4,115

$ 840

$ 4,955


Structure

Structure

33,300

$ 1,832

$ 780

JCC

Girder and Supports

1,203

$ 65

$ -

NY


Magnet Systems

Magnet

288-0.5Q12.75

2

$ 86

360-0.5Q17.00

3

$ 107

720-0.5Q38.25

6

$ 214

BPM (1368)

3,855

$ 181

$ 56

Supports and movers

5931

288

NY


Vacuum Systems

Girder

1,864

$ 105

$ -

NY

non-RF beamline

7,273

$ 400

JW


Diagnostic Regions

Magnets

Supports and movers

949

$ 47.45

28-0.5Q17.00 including movers etc

60-0.5Q38.25 including movers etc

24- Laser wire scanners

112 QBPMs

316

$ 15

$ 1

High Energy polarimeter detectors

$ 738

DS

92 MBBPMs

833

$ 38

$ 3