1.3.2

Main Linac Beam Lines

($000)

1.3.2.1

Conceptual Design (CD1-CD2)

Labor hrs

Labor $

Material $

sub totals

Structure

4,181

$ 230

$ 100

$ 330

Magnet Systems

2,850

$ 153

$ 2

$ 155

Vacuum systems

746

$ 42

$ 42

Diagnostic Regions

959

$ 47

$ 0

$ 47

Totals

8,736

$ 471

$ 102

$ 573


Structure

Structure

3,700

$ 204

$ 100

JCC

Girder and supports

481

$ 26

NY


Magnet Systems

Magnet

288-0.5Q12.75

200

$ 11

CR

360-0.5Q17.00

249

$ 10

CR

720-0.5Q38.25

199

$ 21

CR

BPM (1368)

936

$ 46

$ 2

CR+SS

Supports and movers

1,266

$ 64

NY


Vacuum Systems

Girder and Supports

746

$ 42

NY

non-RF beamline


Diagnostic Regions

Magnets

Supports and movers

380

$ 18.98

28-0.5Q17.00 including movers etc

60-0.5Q38.25 including movers etc

24- Laser wire scanners

112 QBPMs

77

$ 4

$ 0

CR+SS

High Energy polarimeter detectors

92 MBBPMs

503

$ 24

$ 1