| ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
| 1 |
Reviews |
770 days |
Mon 5/24/99 |
Fri 5/3/02 |
|
0% |
| 2 |
CD-1 Design Review |
5 days |
Mon 5/24/99 |
Fri 5/28/99 |
|
0% |
| 3 |
CDR0.4 Progress Review |
0 days |
Mon 11/1/99 |
Mon 11/1/99 |
|
0% |
| 4 |
CDR0.4 Design Review |
5 days |
Mon 5/1/00 |
Fri 5/5/00 |
|
0% |
| 5 |
CDR0.8 Progress Review |
0 days |
Wed 11/1/00 |
Wed 11/1/00 |
|
0% |
| 6 |
CDR0.8 Design Review |
5 days |
Mon 4/30/01 |
Fri 5/4/01 |
|
0% |
| 7 |
CDR1.0 Progress Review |
0 days |
Thu 11/1/01 |
Thu 11/1/01 |
|
0% |
| 8 |
CDR1.0 Design Review |
5 days |
Mon 4/29/02 |
Fri 5/3/02 |
|
0% |
| 9 |
CD-1 |
0 days |
Wed 6/30/99 |
Wed 6/30/99 |
|
0% |
| 10 |
CDR |
0 days |
Mon 7/1/02 |
Mon 7/1/02 |
|
0% |
| 11 |
CD-2 |
0 days |
Tue 12/31/02 |
Tue 12/31/02 |
|
0% |
| 12 |
MPS Electronics System |
915 days |
Wed 6/30/99 |
Wed 1/1/03 |
|
0% |
| 13 |
MPS Conceptual Design |
915 days |
Wed 6/30/99 |
Tue 12/31/02 |
|
0% |
| 14 |
Refine specifications for the overall MPS system |
133 days |
Wed 6/30/99 |
Fri 12/31/99 |
Physicist[30%] |
0% |
| 15 |
Develop the subsystem architecture |
260 days |
Mon 1/3/00 |
Fri 12/29/00 |
Engineer[50%] |
0% |
| 16 |
MPS functional integration into Control
System |
260 days |
Mon 1/3/00 |
Fri 12/29/00 |
Engineer[30%] |
0% |
| 17 |
Develop MPS test scenarios |
261 days |
Mon 1/1/01 |
Mon 12/31/01 |
Software[20%] |
0% |
| 18 |
Reliability study |
261 days |
Mon 1/1/01 |
Mon 12/31/01 |
Engineer[20%] |
0% |
| 19 |
Documentation & CDR Prep |
261 days |
Tue 1/1/02 |
Tue 12/31/02 |
Engineer[50%] |
0% |
| 20 |
Fast Abort System |
915 days |
Wed 6/30/99 |
Tue 12/31/02 |
|
0% |
| 21 |
Document design parameters for fast abort system |
133 days |
Wed 6/30/99 |
Fri 12/31/99 |
Engineer[20%] |
0% |
| 22 |
Produce conceptual design: hardware & software |
130 days |
Mon 1/3/00 |
Fri 6/30/00 |
Engineer[25%],Software[25%] |
0% |
| 23 |
Protoype and test the design |
130 days |
Mon 7/3/00 |
Fri 12/29/00 |
Technician[50%] |
0% |
| 24 |
FAS System Defined |
0 days |
Mon 1/1/01 |
Mon 1/1/01 |
|
0% |
| 25 |
Produce hardware and release software |
130 days |
Mon 1/1/01 |
Fri 6/29/01 |
Engineer[25%],Software[25%] |
0% |
| 26 |
Final test and system documentation |
392 days |
Mon 7/2/01 |
Tue 12/31/02 |
Technician[25%],Drafting[25%] |
0% |
| 27 |
Radiation Detection Devices |
261 days |
Mon 1/1/01 |
Tue 1/1/02 |
|
0% |
| 28 |
Prototype modular PLIC devices |
261 days |
Mon 1/1/01 |
Mon 12/31/01 |
Engineer[10%],Technician[10%] |
0% |
| 29 |
Prototype new PIC devices |
261 days |
Mon 1/1/01 |
Mon 12/31/01 |
Engineer[10%],Technician[10%] |
0% |
| 30 |
Radiation Device Selection Complete |
0 days |
Tue 1/1/02 |
Tue 1/1/02 |
|
0% |
| 31 |
MAID BPM Procedures |
522 days |
Mon 1/3/00 |
Tue 1/1/02 |
|
0% |
| 32 |
Investigate data and processing requirements |
130 days |
Mon 1/3/00 |
Fri 6/30/00 |
Software[30%] |
0% |
| 33 |
Prototype processing modules and test them |
260 days |
Mon 7/3/00 |
Fri 6/29/01 |
Technician[50%] |
0% |
| 34 |
Document findings and interface specifications |
132 days |
Mon 7/2/01 |
Tue 1/1/02 |
Engineer[10%],Software[10%] |
0% |
| 35 |
MPS MAID BPM Processing Design Complete |
0 days |
Tue 1/1/02 |
Tue 1/1/02 |
|
0% |
| 36 |
MPS Data Acquisition Systems |
522 days |
Mon 1/1/01 |
Tue 12/31/02 |
|
0% |
| 37 |
Gather data and formulate test plan |
65 days |
Mon 1/1/01 |
Fri 3/30/01 |
Engineer[50%],Software[50%] |
0% |
| 38 |
Prepare testbed and run tests |
260 days |
Mon 4/2/01 |
Fri 3/29/02 |
Engineer[30%],Technician[50%],Software[20%] |
0% |
| 39 |
Document results and interface requirements |
197 days |
Mon 4/1/02 |
Tue 12/31/02 |
Engineer[50%],Software[50%] |
0% |
| 40 |
Complete MPS Data Acquisition selection |
0 days |
Wed 1/1/03 |
Wed 1/1/03 |
|
0% |