nlclogo.jpg (6796 bytes)

MPS Electrical System: R&D R1 031599


Project Start: 
Project Finish: 
Mon 3/15/99 
Wed 1/1/03 

Tasks


ID Task Name Duration Start Finish Resource Names % Complete
1 Reviews 770 days Mon 5/24/99 Fri 5/3/02   0%
2 CD-1 Design Review  5 days Mon 5/24/99 Fri 5/28/99   0%
3 CDR0.4 Progress Review 0 days Mon 11/1/99 Mon 11/1/99   0%
4 CDR0.4 Design Review  5 days Mon 5/1/00 Fri 5/5/00   0%
5 CDR0.8 Progress Review 0 days Wed 11/1/00 Wed 11/1/00   0%
6 CDR0.8 Design Review  5 days Mon 4/30/01 Fri 5/4/01   0%
7 CDR1.0 Progress Review 0 days Thu 11/1/01 Thu 11/1/01   0%
8 CDR1.0 Design Review 5 days Mon 4/29/02 Fri 5/3/02   0%
9 CD-1 0 days Wed 6/30/99 Wed 6/30/99   0%
10 CDR 0 days Mon 7/1/02 Mon 7/1/02   0%
11 CD-2 0 days Tue 12/31/02 Tue 12/31/02   0%
12 MPS Electronics System 915 days Wed 6/30/99 Wed 1/1/03   0%
13 MPS Conceptual Design 915 days Wed 6/30/99 Tue 12/31/02   0%
14 Refine specifications for the overall MPS system 133 days Wed 6/30/99 Fri 12/31/99 Physicist[30%] 0%
15 Develop the subsystem architecture 260 days Mon 1/3/00 Fri 12/29/00 Engineer[50%] 0%
16 MPS functional integration into Control System  260 days Mon 1/3/00 Fri 12/29/00 Engineer[30%] 0%
17 Develop MPS test scenarios 261 days Mon 1/1/01 Mon 12/31/01 Software[20%] 0%
18 Reliability study 261 days Mon 1/1/01 Mon 12/31/01 Engineer[20%] 0%
19 Documentation & CDR Prep 261 days Tue 1/1/02 Tue 12/31/02 Engineer[50%] 0%
20 Fast Abort System 915 days Wed 6/30/99 Tue 12/31/02   0%
21 Document design parameters for fast abort system 133 days Wed 6/30/99 Fri 12/31/99 Engineer[20%] 0%
22 Produce conceptual design: hardware & software 130 days Mon 1/3/00 Fri 6/30/00 Engineer[25%],Software[25%] 0%
23 Protoype and test the design 130 days Mon 7/3/00 Fri 12/29/00 Technician[50%] 0%
24 FAS System Defined 0 days Mon 1/1/01 Mon 1/1/01   0%
25 Produce hardware and release software 130 days Mon 1/1/01 Fri 6/29/01 Engineer[25%],Software[25%] 0%
26 Final test and system documentation 392 days Mon 7/2/01 Tue 12/31/02 Technician[25%],Drafting[25%] 0%
27 Radiation Detection Devices 261 days Mon 1/1/01 Tue 1/1/02   0%
28 Prototype modular PLIC devices 261 days Mon 1/1/01 Mon 12/31/01 Engineer[10%],Technician[10%] 0%
29 Prototype new PIC devices 261 days Mon 1/1/01 Mon 12/31/01 Engineer[10%],Technician[10%] 0%
30 Radiation Device Selection Complete 0 days Tue 1/1/02 Tue 1/1/02   0%
31 MAID BPM Procedures 522 days Mon 1/3/00 Tue 1/1/02   0%
32 Investigate data and processing requirements 130 days Mon 1/3/00 Fri 6/30/00 Software[30%] 0%
33 Prototype processing modules and test them 260 days Mon 7/3/00 Fri 6/29/01 Technician[50%] 0%
34 Document findings and interface specifications 132 days Mon 7/2/01 Tue 1/1/02 Engineer[10%],Software[10%] 0%
35 MPS MAID BPM Processing Design Complete 0 days Tue 1/1/02 Tue 1/1/02   0%
36 MPS Data Acquisition Systems 522 days Mon 1/1/01 Tue 12/31/02   0%
37 Gather data and formulate test plan 65 days Mon 1/1/01 Fri 3/30/01 Engineer[50%],Software[50%] 0%
38 Prepare testbed and run tests 260 days Mon 4/2/01 Fri 3/29/02 Engineer[30%],Technician[50%],Software[20%] 0%
39 Document results and interface requirements 197 days Mon 4/1/02 Tue 12/31/02 Engineer[50%],Software[50%] 0%
40 Complete MPS Data Acquisition selection 0 days Wed 1/1/03 Wed 1/1/03   0%

Resources


ID Name Group Max Units Peak Units
1 Physicist   50% 30%
2 Engineer   250% 115%
3 Drafting   100% 25%
4 Technician   100% 100%
5 Software   100% 95%

Assignments


Task ID Task Name Resource Name Work Start Finish % Work Complete
14 Refine specifications for the overall MPS system Physicist 319.2 hrs Wed 6/30/99 Fri 12/31/99 0%
15 Develop the subsystem architecture Engineer 728 hrs Mon 1/3/00 Fri 12/29/00 0%
16 MPS functional integration into Control System  Engineer 520 hrs Mon 1/3/00 Fri 12/29/00 0%
17 Develop MPS test scenarios Software 417.6 hrs Mon 1/1/01 Mon 12/31/01 0%
18 Reliability study Engineer 417.6 hrs Mon 1/1/01 Mon 12/31/01 0%
19 Documentation & CDR Prep Engineer 1,044 hrs Tue 1/1/02 Tue 12/31/02 0%
21 Document design parameters for fast abort system Engineer 212.8 hrs Wed 6/30/99 Fri 12/31/99 0%
22 Produce conceptual design: hardware & software Engineer 260 hrs Mon 1/3/00 Fri 6/30/00 0%
22 Produce conceptual design: hardware & software Software 260 hrs Mon 1/3/00 Fri 6/30/00 0%
23 Protoype and test the design Technician 520 hrs Mon 7/3/00 Fri 12/29/00 0%
25 Produce hardware and release software Engineer 260 hrs Mon 1/1/01 Fri 6/29/01 0%
25 Produce hardware and release software Software 260 hrs Mon 1/1/01 Fri 6/29/01 0%
26 Final test and system documentation Technician 784 hrs Mon 7/2/01 Tue 12/31/02 0%
26 Final test and system documentation Drafting 784 hrs Mon 7/2/01 Tue 12/31/02 0%
28 Prototype modular PLIC devices Engineer 208.8 hrs Mon 1/1/01 Mon 12/31/01 0%
28 Prototype modular PLIC devices Technician 208.8 hrs Mon 1/1/01 Mon 12/31/01 0%
29 Prototype new PIC devices Engineer 208.8 hrs Mon 1/1/01 Mon 12/31/01 0%
29 Prototype new PIC devices Technician 208.8 hrs Mon 1/1/01 Mon 12/31/01 0%
32 Investigate data and processing requirements Software 312 hrs Mon 1/3/00 Fri 6/30/00 0%
33 Prototype processing modules and test them Technician 884 hrs Mon 7/3/00 Fri 6/29/01 0%
34 Document findings and interface specifications Engineer 105.6 hrs Mon 7/2/01 Tue 1/1/02 0%
34 Document findings and interface specifications Software 105.6 hrs Mon 7/2/01 Tue 1/1/02 0%
37 Gather data and formulate test plan Engineer 260 hrs Mon 1/1/01 Fri 3/30/01 0%
37 Gather data and formulate test plan Software 260 hrs Mon 1/1/01 Fri 3/30/01 0%
38 Prepare testbed and run tests Engineer 416 hrs Mon 4/2/01 Thu 11/29/01 0%
38 Prepare testbed and run tests Technician 1,040 hrs Mon 4/2/01 Fri 3/29/02 0%
38 Prepare testbed and run tests Software 416 hrs Mon 4/2/01 Fri 3/29/02 0%
39 Document results and interface requirements Engineer 788 hrs Mon 4/1/02 Tue 12/31/02 0%
39 Document results and interface requirements Software 788 hrs Mon 4/1/02 Tue 12/31/02 0%

This page owned & maintained by Nixx and R. Larsen