NLC 8 Pack Project 

Progress Photos

The site for the installation of the modulator and racks of the 8 Pack Project is on the north side of End Station B, next to the NLCTA housing.  The pictures below show the progress made since the start of the project on October 1st, 2001.

 

October 15, 2001 October 30, 2001 November 2, 2001 November 5, 2001
End Station B Site before work starts  Discussing Layout Mostly Clean

Floor cleaned and polished

January 18, 2002

February 5, 2002 February 6, 2002 March 1, 2002
Locations marked by tape First Installation

Ground Breaking Party 2

Oil containment curb in place

Oil containment curb in place

First coat of sealant is down

First coat of sealant is down

 

Page Last Updated On | 04/22/02 | Owner: Scott Anderson