8-Pack Project Meeting Notes

Date:  August 21, at 10:00 AM

Bldg. 214 Fuji conference room

 

 

 

An 8-Pack Project Meeting was held on August 21, at 10:00 AM in bldg. 214 Fuji conference room.  Attached are copies of the presentation material.  A status of work in progress was presented by each of the project leaders. 

 

Conventional Facilities – J. Sevilla

                Inspected site for utilities.

                Cost estimate started.

                Need loads for cooling flowrates and DP requirements.

                Need to evaluate temperature control in racks.

LLRF System – S. Smith

                Controls conceptual design will be ready this time next week.

                Cost estimates will come a week later.

Modulators - R. Cassel

Question - Who will decide whether to align kylstron to waveguide or waveguide to klystron?

                Question - Who is costing tank, concrete, etc?

                Question – Is the 8-Pack system separate from the 4-Pack system as originally planned?

Control & DAQ – R. Fuller

                Have tentative cost estimate modeled on existing equipment .

                The cost data needs to be converted to new consolidated format per S. Anderson.

M-K System – R. Larson

                The cost estimate will be approximately 1 week late.  Its impact should be minimal.

PPS System – N/A

 

Vacuum Instrumentation – E. Hamner

                Need parts count form C. Rago.

                Question – What degree of detail should costs be estimated (nuts and bolts)?

Racks – R. Fuller

                $25K cost is based on 5 double racks.

                Need more information to improve estimate.

Cable Plant – R. Fuller

                Question – Should some or all labor be estimated as in-house or outside labor?

Per D.  Burke, this project is R&D so no Davis-Bacon should be used in costing unless necessary.

Klystrons – G. Caryotakis

                Cost estimate and schedule is preliminary and is not released.

                There is a slight schedule delay on delivery of the first 4 tubes but they are not on critical path.

                Tube cost is based on 12 starts with 8 to be installed and 2 spares.

                The cost to support 8-Pack test is $3.3M.

SLED/DLDS/Loads – C. Rago

                Collecting cost information for next week schedule will come much later.

                See attachment.

Coordination – S. Anderson

                See attachments.

The project coordination drawing packages will be done in Solid Edge.  Drawings and schematics made with other tools are fine and could be preferable.  Non-Solid Edge files will be ported into Solid Edge when necessary.

                Need to distribute scheduling template.

                Estimate costs at a level of effort to support D. Schultz needs.

                Spares should be noted in estimate. Do not include contingency.

                Identify task labor hours with names for SLAC FTE employees.

Systems Engineering – McKee

                See attachment

 

Following are the action items:

1.       Cost and schedules. All estimators

2.       Send facilities information questionnaire to Klystron. Sevilla

3.       How to accommodate alignment of klystron with waveguide. Rago/Cassel

4.    Who is costing klystron tank, concrete, etc?                 Cassel

5.        Will 4-pack and 8-pack be completely separate systems?              Schultz 

                        6.    Provide a template for scheduling.                                           Scott                      

 

If you have any questions please contact either S. Anderson at 4590 or me at 2835.  Thank you.

                             

 

 

 

 

                                Scott Anderson                                                                                                                                   Bobby McKee