8 pack meeting notes October 9th 2001
Agenda:
1.
Davis-Bacon
determination
2.
Klystron
progress report and plans
3.
Budget and
Schedule.
Notes:
- Davis
Bacon Determination
- D.
Schultz compiled a list of work that detailed which work should be Davis-Bacon
and which work is not. He is
submitting this list to the Davis-bacon committee which will review it
and then it will be sent to the Oakland DOE office.
- K.
Jobe pointed out that RF cable should be in house because all of the
previous NLCTA cables were contract installed and they all had to be
reterminated.
- Klystron
Update J. Cournelle
- Update
presentation (.ppt)
- First
XP-3 started exhaust on 10/5/01.
- There
are three XP-3 tubes being built now.
The first is a SLAC tube, the second is a CPI tube and the third
is another SLAC tube. The first
two tubes have all of the parts needed to finish them. The third needs a few more parts. A fourth tube needs many parts to be
finished.
- Question: Should a Toshiba X-band tube be
purchased, so tubes made by all manufactures can be tested?
- Question: Can design specification be put on the
web? Yes.
- Question: What is the efficiency? 60% is the design
- Question:
What happens if the efficiency is low?
Will need more power form the modulator.
- Question: What are the radiation shielding
requirements for the XP-3? The
lead used for shielding should be designed into the klystron assembly and
this assembly should have an earthquake specification. Will be address offline. The first two or three klystrons
tested in the Klystron Lab will have many diagnostics and will be tested
in a lead house, so they will need to have lead shielding added
- TWTA
J. Cournelle
- What
are the output specifications for the TWTA. S. Gold should have them and J. Frisch shold be the one to
check them.
- TWTAs
should have a rack near the klystrons.
There will be two racks near the klystrons.
- Water
System J. Sevilla
- Water
pressure requirements are 120 PSI.
The current available pressure in ESB is 80 PSI. Will need to buy a booster pump to
reach 120 PSI.
- Chiller
will also be purchased to cool the PM (permanent magnets) which focus the
klystron beam.
- Question: Does the modulator cooling need to be de-aired? To be determined offline.
Action Items:
- Determine
beamline layout. Adolphsen, Rago
- Earthquake
support plan. Jobe, Rago.