8 pack meeting notes September 25th, 2001
Agenda:
- Progress reports All groups
- PEP II Downtime schedule S. Anderson
- Raised Floor Proposal -J. Sevilla
Notes:
- Modulator
R. Cassel
- Received
draft klystron specification for protection instrumentation and power
requirements. Some details are
still needed, but it is a good starting point.
- Need
1 rack near modulator stack.
- Controls
R. Chestnut
- Need
to know scope of LLRF work for complete estimate. LLRF should have a first pass design
next week.
- PPS
System/ ES&H P. Bong & K. Jobe
- K.
Jobe will make presentation to ES&H about 8 pack project sometime in
October. Will consult with D.
Schultz about presentation.
- Vacuum
Instrumentation - E. Hamner
- Want
to purchase vacuum power supplies in October. Need to review count and specifications before
purchase. (See Action Item 1)
- Klystrons have 6 ion pumps each. Need to understand power supply
needs. (See Action Item 1)
- Cable
Plant P. Rodriguez
- Presented
layout of trays near modulators and racks. Trays fit underneath the raised floor area.
- Need
to get layout of SLED II and DLDS system on top of NLCTA shielding. (See
action item 2)
- Conventional
Facilities F. Asiri
- Presented
raised floor proposal. One cost
bid is for $35,000 for 1200 sq ft.
i.
There is a safety concern that the removable tiles must lock
into place even when tiles next to them are removed. This should be reviewed.
- RF
Distribution J. Cournelle
- Review
SLED II system next week.
- Klystron
J. Cournelle
- First
XP-3 will be pumped down next week.
- Specification
given to Modulator group (see #1).
- 8-Pack
Management and System engineering
- Schedule
S. Anderson
i.
Showed Tech division running and downtime schedule. PEP IIs downtime starts July 1st and goes until the end of
September.
ii.
The 8 Pack project will probably receive little support in the
weeks prior and all during the PEP II downtime.
iii.
8 pack work should be included in downtime scheduling.
- Drawing Numbers M. Ofengender
i.
Meyer Ofengenden will keep track of drawing number
assignments. Blocks of assembly drawing
numbers have been allocated to the various groups. To see assignments go to web page at: drawings
page
- Account
numbers - S. Anderson
i.
New charge account numbers for the 8-Pack project should be
ready in early October.
Action Items:
- Review
pump layout and count before purchase of pump powers supplies. Make sure klystron pump needs are met
by pumping scheme. Carl Rago.
- Need
to give P. Rodriguez (Cable Plant ) layout of SLED II and DLDS systems so
he can determine cable tray layout on top of NLCTA shielding. B. McKee
- Review
raised floor/ cable tray proposal vs. modulator and rack layout. D.
Schultz
- How
is the raised floor proposal effected by the rack access?
- How is the raised floor proposal effected by the new
idea of side access to the modulator tank?
- How
does a possible 3 10 wide secondary containment oil tank effect the
raised floor proposal?
- How
does assemble scenarios of the 8-Pack effect the raised floor proposal?