8 pack meeting minutes - August 28th 2001
Agenda:
1) Schedule & Budget.
Continuing from last week, Klystron, SLED/DLDS/Loads, M&K controls,
PPS, Cabling
2) Updated floor plan in ESB
3) Areas of responsibility, and eliminating gaps in
responsibilities between groups
Notes:
- Conventional
Facilities J. Sevilla
- Needs
Requirements
i.
Concrete
ii.
Drilling in shielding
iii.
NLCTA downtime
iv.
Location
- Davis
Bacon labor?
- Cost
Done. Rough Schedule.
- LLRF
S. Smith
- Cost
presentation
- No
formal cost or schedule. Need
requirements and design first.
- Modulators
R. Cassel
- Plan
is to move existing 4 dog down to NLCTA for Phase I, then build a
separate 8 pack stand and modulator stack for Phase II.
- Cost
done. Rough schedule.
- Controls
and DAQ B. Fuller
- Need
to know how many crates and of what types. Have made first guess.
- There
will be programmer conflicts with present programs at PEP II and NLCTA
etc.
- Costs
done.
- ES&H
K. Jobe
- Need
to know the safety requirements before costs can be given. From what is known ES&H costs
should be minimal.
- Vacuum
Electronics - E. Hamner
- DLDS
uses 66 vacuum pump supplies.
- Supplies
will power multiple pumps.
- Cost
done. Schedule depends on layout.
- Racks. M. Ortega
- 16
racks total, includes
i.
Bucking coil and solenoid supplies. Actually shouldnt need solenoid supplies.
ii.
LBL style racks
iii.
Water cooling not included
iv.
Special RF racks (i.e. temperature controlled) not included.
- Costs
done.
- Cable Plant
P. Rodriguez
- Need
layout and number of cables to give cost. Will have meeting soon to determine.
- Klystron
J. Cournelle
- Cost
estimate for XP-3s given.
i.
Phase I. 4 klystrons,
no spares
ii.
Phase II. 8 starts to
make 6 klystrons. So 4 more plus 2 spares.
- No
TWT cost. Next week.
- RF Distribution C. Rago
- Cost
given for both phases. Cost
includes 20% overstock for materials
- Loads
included?
- Couplers
not in estimate.