8 pack meeting minutes - August 14th 2001
Agenda:
1) Schedule & Cost estimates
2) Areas of responsibility
3) Questions
Notes:
- Questions
- Where
are the modulator, modulator power supply, racks, SLED, DLDS placed in
ESB?
- What
are the klystron output requirements?
- What
shielding is needed?
- Will
the 4-Pack be running while the 8-Pack is installed?
- Cost
Estimates and Schedules
- Cost
estimates and schedules due by 8/28/01
Action Items:
- Get
latest drawings for ESB and NLCTA.