8 pack meeting notes - January 22, 2002

 

Agenda:

1.     Purchasing - Schultz

2.     Drawing update - Eriksson

3.     Cabling specification – Rodriguez

4.     LCW System - Sevilla

 

Notes:

1.     Purchasing –Schultz

2.     Drawing Update – Eriksson

a.      Drawing in DXF form exists and can be sent to anyone who requests it.  A Tiff image can also be seen.

b.     A hard copy of the floor plan is posted on the white board in the Fuji conference room

c.     On Thursday 1/31/02 the drawing will become official and released, so make comments and changes requests before 1/30/02. 

3.     Cabling specification – Rodriguez

a.     Must have the following to finish cable plant design

1.     Equipment Layout

2.     Formal Device name and numbering system – Action Item

1.     Each device should have a unique number

b.     Floor height is 28 inches

c.     How will the vacuum cable plant move from Phase I to II?  Meeting on Friday 1/25/02 11:00 AM

4.     LCW Systems – Sevilla

Action Items

1.     Formal Device name and numbering system – Jobe, Rago.