8 pack meeting notes – January 15, 2001

 

Agenda:

1)     Upcoming scheduled reviews

2)     Project Schedule

 

Notes:

1)     8-pack reviews last week

a.      LLRF  -  Wednesday

b.     Racks  -  Thursday

 

2)     8-pack reviews upcoming and pending,  Jan. 2002

a.      Modulator  -  Thursday 1-17, 1:30, Fuji Room

1)     Second pass at Modulator/Klystron stand design

2)     Preparation for Earthquake committee review 1-17, 11:00

3)     Beginning detailed drawings

4)     Budget and Schedule

3)     8-Pack reviews next week

a.      Controls

b.     Special Instrumentation

4)     8-pack Project System Review,  Feb. 22 2002

a.      Schedule to be distributed by B. McKee

5)     RF Distribution system – beginning a weekly progress meeting

6)     4 Pack Project Schedule –Scott Anderson