Index

Page No.

1. Major Changes in Configuration since the Lehman Review in May 1999 1

2. Configuration for CDR 0.4, September 2000

1. Major Changes in Configuration since the Lehman Review in May 1999

2. Current Configuration of the NLC Conventional Facilities

Facility

Configuration for CDR 0.4

Injector

Sources & Boosters: Positron: 2824.08 LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Electron: 941.36 LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Tunnel ID: 14 FT

Shafts: 6 access shafts 23 FT in diameter

3 utility shafts 8 FT in diameter

Cooling System: Two mechanical pads supplied with chilled water from central cooling plant. Each pad provides chilled water (for active tunnel air-cooling, for rack cooling and for HVAC systems in klystron galleries and support buildings) and LCW (for cooling structures, waveguides and electro-magnets, and for cooling klystrons and modulators). Chilled water system total capacity is TBD tons and LCW cooling system total capacity is TBD GPM of LCW for a heat load of TBD kW. Each pad also provides 100 CFM of compressed air at 90 PSI for operating vacuum valves and other equipment.

Electrical System: demand: TBD MW; 15 substations, 34.5 - 0.48 kV

No. TBD Support Buildings: TBD SF total

 

Damping Rings: Positron: PDR 715.04 LF PTM 196.80 LF MDR 974.16 LF

(Cut & Cover: TBD %; Shallow Bored: TBD %)

Electron: MDR 974.16 LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Tunnel ID 14 FT

Shafts: 3 access shafts 23 FT in diameter

3 utility shafts 10 FT in diameter

Cooling System: Three mechanical pads, one for each ring, supplied with chilled water from central cooling plant. Each pad provides chilled water (for active tunnel air cooling, for rack cooling and for HVAC systems in support buildings) and LCW (for electro-magnets, vacuum and RF loads, and for cooling klystrons and modulators and crab cavities). Three dedicated LCW systems provide cooling for the damping ring dumps. Chilled water system total capacity is TBD tons and LCW cooling system total capacity is TBD GPM of LCW for a heat load of TBD KW. Each pad also provides 100 CFM of compressed air at 90 PSI for operating vacuum valves and other equipment.

Electrical System: demand: TBD MW; four substations, 34.5 - 0.48 kV

No. TBD Support Buildings: TBD SF in total

 

Pre-Linacs: Positron: 2066.40 LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Electron: 2066.40 LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Tunnel ID: 14 FT

Shafts: 2 access shafts 23 FT in diameter

4 utility shafts 8 FT in diameter

Cooling System: Four mechanical pads supplied with chilled water from central cooling plant. Each pad provides chilled water (for active tunnel air cooling, for rack cooling and for HVAC systems in klystron galleries and support buildings) and LCW (for electro-magnets, collimators, vacuum and RF loads, and for cooling klystrons and modulators). Chilled water system total capacity is TBD tons and LCW cooling system total capacity is TBD GPM for a heat load of TBD KW. Each pad also supplies 100 CFM of compressed air at 90 PSI for operating vacuum valves and other equipment.

Electrical System: demand: TBD MW; 12 substations, 34.5 - 0.48 kV

No. TBD Support Buildings: TBD SF in total

 

 

Main Linac

Main Linac: Positron: TBD LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Electron: TBD LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Tunnel ID: 14 FT:

Shafts: 10 access shafts 23 FT in diameter

44 utility shafts 10 FT in diameter

Cooling Systems: Forty-four mechanical pads, one for each linac sector, supplied with chilled water from central cooling plant. For the RF sectors, each pad provides chilled water (for active tunnel air cooling, for rack cooling; and for klystron gallery HVAC systems) and LCW (for structures, electro-magnets and RF elbows; and for cooling klystrons and modulators). For the non-RF sectors, each pad provides chilled water for active cooling of tunnel air, for rack cooling and for klystron gallery HVAC systems. The mechanical pads for the final sector in each linac also provide LCW for the 13 MW beam dumps at the ends of the main linacs. Chilled water system total capacity is approximately 20,000 gpm for a total heat load of approximately 12,500 tons and the LCW cooling system total capacity is approximately 88,500 GPM for a heat load of 58,225 kW at 500 GeV.

Electrical System:

Demand: TBD MW

RF Sectors: 22 dual substations (one 34.5 - 0.48 kV transformer for motors, I&C racks

and power supply racks; and one 34.5 - 1.3 kV transformer & rectifier to

supply 2.2 kV dc for modulators)

Non-RF Sectors: 22 substations (34.5 - 0.48 kV

No. TBD Klystron Galleries: TBD SF each; TBD SF in total.

Beam Delivery

Beam Delivery: Positron: TBD LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

Electron: TBD LF (Cut & Cover: TBD %; Shallow Bored: TBD %)

(IRT1 includes all facilities and supporting services. For IRT2, only the basic structure is provided. Electrical/mechanical systems will be installed when the second detector is built.)

Tunnel ID: 14 FT

Shafts: 5 access shafts 23 FT in diameter

6 utility shafts 8 FT in diameter

Cooling Systems: Six mechanical pads for IRT1 supplied with chilled water from central cooling plant. Each pad provides chilled water (for HVAC systems for the support buildings and for active tunnel air cooling, using air handling units) and LCW (for electro-magnets and, where applicable, for collimators and dumps). Chilled water system total capacity is TBD tons and the LCW cooling system total capacity is TBD GPM for a total heat load of TBD KW. Each pad also provides 200 CFM of compressed air at 90 PSI for operating vacuum valves and other equipment. The huts have air-cooled HVAC systems with a total installed cooling capacity of TBD tons

Electrical System: demand: TBD MW; 12 substations, 34.5 - 0.48 kV

Huts: No. TBD with total area of TBD SF

Support Buildings: No. TBD with total area of TBD SF

 

Interaction Region

2 IR complexes: TBD SF each.

(For IR2, only the basic structure is provided.)

Shafts: 1 access shaft 23 FT in diameter

2 utility shafts 12 FT in diameter

Cooling systems: Two mechanical pads, for the IR1 complex only, supplied with chilled water from the central cooling plant. The pads provide chilled water (for HVAC systems for enclosed spaces) and LCW (for magnets and technical system components and for the two final 13 MW beam dumps). The chilled water system total capacity is approximately 3,200 GPM for a heat load of 2,000 tons of refrigeration and the LCW cooling system total capacity is approximately 5,700 GPM for a total heat load of 24,000 KW. Each pad also provides 200 CFM of compressed air at 90 PSI.

Electrical System (IR1): TBD demand; four substations, 34.5 - 0.48 kV

Site Development

Land acquisition: 7900 acres

 

Off-Site Support - TBD

Alignment Network: 1493 monuments

Construction Support/Spoil Disposal: TBD

 

Site Preparation

Clearing/Grading: TBD acres

Drainage: TBD LF

Fencing: TBD LF

Irrigation: TBD acres

 

Electrical System: TBD MW capacity

Three main substations: 230 kV/34.5 kV and three-way, cross-tied ring bus distribution system

Three 34.5 - 19.9 kV solidly grounded overhead distribution circuits

 

Waste and Water Systems:

On-site water treatment plant for peak population of TBD

TBD LF water distribution system

On-site sewage treatment plant for peak population of TBD

TBD LF sanitary sewer lines

Electrical System: five substations, 34.5 - 0.48 kV

 

Communications Systems:

PBX for No. TBD lines

TBD LF telephone cable

TBD LF SCADA cable

 

Roads/Paving: TBD SY

Campus

Central Lab: 367,000 SF

1,000-seat auditorium

Electrical System: two substations, 34.5 - 0.48 kV

 

 

 

Heavy Works

Two heavy assembly buildings: 86,000 SF

Four light assembly buildings: 80,000 SF

Electrical System: two substations, 34.5 - 0.48 kV

 

Shops: three buildings: 30,100 SF

Electrical System: two substations, 34.5 - 0.48 kV

 

Warehouse:

Two warehouse buildings: 80,000 SF

Bottled gases building. 6,000 SF

Electrical System: two substations, 34.5 0.48 kV

 

Security/Emergency Services:

Security services facility and outpost buildings 1,600 SF

Emergency response center: 13,000 SF

Medical facility 2,000 SF

ES&H facility: 2,000.SF

Electrical System: one substation, 34.5 - 0.48 kV

 

Vehicle Service/Grounds Maintenance

Three buildings: 13,000 SF total area

Electrical System: one substation, 34.5 - 0.48 kV

 

Centralized Cooling Plant: TBD SF

Provides chilled water for cooling systems in beam-line housings; chilled and hot water for campus HVAC systems; and LCW and compressed air for the laboratory area.

Electrical system: four substations, 34.5 - 0.48 kV

 

Control/Communications:

Control Room: 10,000 SF

Operations Center: 15,000 SF

Communications 5,000 SF

Electrical System: three substations, 34.5 - 0.48 kV